@ -38,11 +38,13 @@ Have prototype system running by April, 2021 for public review, move to producti
|
|||
|
||||
| Dates | Milestones |
|
||||
| ------------------- | :------------------------------------------------------------------------------------------------------------------------------------: |
|
||||
| 09/14/20 - 9/21/20 | Review Technical Specs, existing code/documentation, and implementation goals for deeper understanding of technical aspects of problem |
|
||||
| 09/25/20 | Deliver implementation plan and user stories for dev team to iteratively implement; allowing the dev team to reevaluate any cases. |
|
||||
| 09/28/20 - 04/30/21 | Main Development Period: Iteratively develop user stories several sprints. Demo new features at the end of sprints for feedback. |
|
||||
| 04/30/21 | Final demo of new features |
|
||||
| 04/30/21 - 05/14/21 | QA period to resolve issues and bugs. Final preparation for product release |
|
||||
| 09/14/20 - 9/21/20 | Review existing code/documentation, and implementation goals for deeper understanding of technical aspects of problem |
|
||||
| 09/21/20 - 12/02/20 | Document requirements of PG deployment environment and evaluate technology options. |
|
||||
| 10/02/20 | Deliver user stories for dev team to iteratively implement; allowing the dev team to reevaluate any cases. |
|
||||
| 10/09/20 | Deliver implementation plan detailing technical feasability and decisions. Document what tools and technologies will be used. |
|
||||
| 10/12/20 - 03/19/21 | Main Development Period: Iteratively develop user stories several sprints. Demo new features at the end of sprints for feedback. |
|
||||
| 03/19/21 | Final demo of new features |
|
||||
| 03/19/21 - 04/30/21 | QA period to resolve issues and bugs. Final preparation for product release |
|
||||
|
||||
_Dates/Milestones are tentative and subject to change._
|
||||
|
||||
|
|